Project Timeline & Labor Hours Estimator

Estimate total labor hours and project duration based on task scope, crew size, daily work hours, and productivity factors.

Formulas Used

Base Labor Hours = Scope of Work ÷ Productivity Rate

Adjusted Labor Hours = Base Labor Hours ÷ Efficiency Factor

Total Labor Hours = Adjusted Labor Hours × (1 + Contingency % ÷ 100)

Crew-Hours per Day = Crew Size × Work Hours per Day

Project Duration (days) = Adjusted Labor Hours ÷ Crew-Hours per Day

Duration with Contingency = Total Labor Hours ÷ Crew-Hours per Day